NEW QUESTION 20
Assume that the following test cases have been executed at the end of the first week of test execution: TC-001, TC-002 and TC-007. All these tests are 'passes'.

What is the MINIMUM number of the remaining test cases that must be successfully executed to fulfill the EX1 exit criteria?
K3 2 credits

  • A. 0
  • B. 1
  • C. 2
  • D. 3

Answer: B

 

NEW QUESTION 21
Test Management
Consider an agile team adopting Extreme Programming (XP) with five developers and one tester without any coding experience.
To which of the following activities would you expect the tester will contribute most?

  • A. Developing unit tests
  • B. Supporting the customer in the execution of acceptance testing
  • C. Executing unit tests
  • D. Planning and executing tests during the integration test phase to detect interface defects

Answer: B

 

NEW QUESTION 22
Assume you have some data related to confirmation testing during system testing of a past project.
In that project 240 bug reports have been opened once, 80 were opened twice, 10 were opened three times and no bug reports have been opened more than three times.
You estimate that a bug report, which has failed its confirmation test, costs, on average, 3 person-hours.
Which of the following statements correctly describe the value of these confirmatory testing activities based on cost of quality?
K3 2 credits

  • A. 340 person-hours have been spent on the project during the system testing phase, because of the failed confirmation tests and this cost belongs to the costs of external failure
  • B. 340 person-hours have been spent on the project during the system testing phase, because of the failed confirmation tests and this cost belongs to the costs of internal failure
  • C. 300 person-hours have been spent on the project during the system testing phase, because of the failed confirmation tests and this cost belongs to the costs of internal failure
  • D. 300 person-hours have been spent on the project during the system testing phase, because of the failed confirmation tests and this cost belongs to the costs of detection

Answer: C

 

NEW QUESTION 23
Test Tools and Automation
In your organization the following tools of the same vendor are currently in use: a requirements management tool, a test management tool and a bug tracking tool.
You are the Test Manager.
You are currently evaluating a test automation tool of the same vendor (to complete the vendor's tool suite) against an interesting open-source test automation tool under the GNU GPL (General Public License).
There are no initial costs associated to that open-source tool.
Which of the following statements associated to the selection of the open-source tool is correct in this scenario?
Number of correct responses: 1
K2 1 credit

  • A. The open-source tool can be modified but only if the community of developers of that tool gives you the formal permission to modify it
  • B. There are no initial costs for the open-source tool because open-source tools are usually low-quality, while vendor tools have always a better quality than the corresponding open-source tools
  • C. The open-source tool can be modified but it can't be distributed further in any way
  • D. There are no initial costs for the open-source tool but you should carefully consider the costs associated to the integration with the existing tools and also evaluate the recurring costs

Answer: D

 

NEW QUESTION 24
Test Management
You are the Test Manager of a new project aimed at developing a software system that must be certified at level B of the DO-178B standard. The project will follow a V-Model software development life cycle and it will have four formal levels of testing: component, integration, system and acceptance testing.
You must produce the test plan documentation for this project by providing an adequate coordination across the four levels of testing in order to assure auditability.
Which of the following answers would you expect to best describe how to organize the test plan?

  • A. Produce four separate detailed level test plans, one for each level, without a master test plan
  • B. Produce a master test plan that covers three levels (component, integration, system test) and a separate acceptance test plan
  • C. Produce a master test plan describing the relationship between the four levels, and four separate detailed level test plans, one for each level
  • D. Produce a single master test plan that covers in detail all four levels, describing the particular activities for all test levels

Answer: C

 

NEW QUESTION 25
Test Management
Which of the following statements, about the test reporting activities for a project adopting an iterative lifecycle model with very short iterations (e.g. two weeks iterations), is correct?

  • A. Test reporting activities are not important for projects adopting an iterative lifecycle model with short iterations
  • B. Test reporting activities are less important for projects adopting an iterative life cycle model with short iterations. They should be performed at the end of the last iteration
  • C. Test reporting activities are still important with an iterative lifecycle. The reports can be used to conduct post-iteration review sessions before starting with the next iteration
  • D. Test reporting activities can't be influenced by the use of an iterative lifecycle model with short iterations

Answer: C

Explanation:
Section: Test Management

 

NEW QUESTION 26
Test Management
You are working on a project to develop an authentication system for an e-commerce website. This system provides two features: Registration and authentication. Two different development teams develop these two features.
There is a high likelihood that the delivery of the authentication feature to the test team will be three weeks later. To complete the registration the user must provide the following registration inputs: Name, surname, birthdate, fiscal code and he/she can select a username and a password.
A registered user can be a special user or a normal user. To be identified as a special user, he/she must also provide, during the registration process, a voucher possibly received from the IT department.
Access is granted only if a user is registered and the password is correct: In all other cases access is denied. If the registered user is a special user and the password is wrong, a special warning is shown on the system console.
You are currently performing a quality risk analysis using FMEA.
Based only on the given information, which of the following is NOT a product risk that could be identified during the quality risk analysis?
Number of correct responses: 1
K4 3 credits

  • A. The late delivery of the authentication feature to the test team causes delays in the start of test execution and this could result in a shorter test period
  • B. The authentication system grants access to a normal user with a wrong password
  • C. The authentication system denies access for a special user with a wrong password, but doesn't display a special warning on the system console
  • D. The authentication system grants access to a special user with a wrong password

Answer: A

 

NEW QUESTION 27
During the system testing phase a tester from your test team observes a failure in the system under test and he/she decides to create an incident report. The incident report is currently in a "new" state, indicating it needs to be investigated.
Which THREE of the following information items can't yet be present in the incident report?
K3 2 credits (2 credits out of 3 credits correct, 1 credit point)

  • A. Steps to reproduce the failure, including screenshots, database dumps and logs where applicable
  • B. The actual and the expected result highlighting the failure
  • C. The lifecycle phase in which the defect has been introduced
  • D. What really caused the failure (actual cause)
  • E. The type of defect that caused the failure

Answer: C,D,E

 

NEW QUESTION 28
You can count on well-written requirements, but you can't count on an adequate contribution of the stakeholders to the quality risk analysis. You have to mitigate the insufficient contribution of the stakeholders because the risk-based testing approach shall minimize the product risks. Your test team has one expert tester in security testing.
Which of the following test activities would you expect to be the less important in this context?
Number of correct responses: 1
K4 3 credits

  • A. Extract from the defect tracking system of the previous project all the security defects and failures, and classify them to support design and execution of specific tests
  • B. Perform exploratory testing sessions with adequate charters covering security aspects
  • C. Automate all functional and non-functional system tests
  • D. Apply systematic and exploratory testing for integration and system test

Answer: C

 

NEW QUESTION 29
Testing Process
The following are the exit criteria described in the test plan of a software product:
EX1. The test suite for the product must ensure that at least each quality risk item is covered by at least one test case (a quality risk item can be covered by more test cases).
EX2. All test cases in the test suite must be run during the execution phase.
EX3. Defects are classified into two categories: "C" (critical defect) and "NC" (non-critical defect). No known C defects shall exist in the product at the end of the test execution phase.
Which of the following information is useless when the specified exit criteria is evaluated?

  • A. A chart, showing the trend in the lag time from defect reporting to resolution, extracted from the defect tracking system
  • B. A list of all the open defects with the associated classification information extracted from the defect tracking system
  • C. The execution status of all the test cases extracted from the test management tool
  • D. A traceability matrix showing the relationships between the product risk items and the test cases

Answer: A

Explanation:
Section: Testing Process

 

NEW QUESTION 30
Reviews
Consider the following list of statements about audits and management reviews:
I. Audits are usually more effective than management reviews at finding defects II. Audits and management reviews have the same main goals, the only difference is related to the roles and level of formality III. A typical outcome of an audit includes observations and recommendations, corrective actions and a pass/fail assessment IV. An audit is not the appropriate mechanism to use at the code review in order to detect defects prior to dynamic testing Which of the following statements is true?
Number of correct responses: 1
K2 1 credit

  • A. II. and III are true; I. and IV. are false;
  • B. I. and III. are true; II. and IV. are false;
  • C. I, III and IV are true; II. is false;
  • D. III. and IV. are true; I and II are false;

Answer: D

 

NEW QUESTION 31
After the presentation, you are asked to explain the chart.
Assume you have applied a full risk-based testing strategy.

Which of the following answers would you expect to best describe the pie chart?
K4 3 credits

  • A. Only the lowest-risk items, tests and bugs should remain in the blue and red areas. Therefore the application can be released at any time subject to management of the items identified in those areas
  • B. According to the full risk-based testing strategy applied, it is very likely that the highest-risk items, tests and bugs remain in the blue and red areas. Therefore, it is very risky to release the application
  • C. 97 percent of the risk items has been tested. No open bugs or test failures remain. Only 3 percent of risk items remains to be covered by the remaining test
  • D. All the risk items have been covered with tests. No more risk items remain to test

Answer: A

 

NEW QUESTION 32
You are following a risk-based testing strategy. The test execution time is very limited. Assume that all the product risk items require more or less the same level of test effort.

Which of the following answers describes the best execution schedule in this scenario?
Number of correct responses: 1
K3 3 credits

  • A. 1- Test the correct pre-activation of the Smart Card
    2- Test the correct activation of the Smart Card
    3- Test the correct charge of the Smart Card with the required contents
    4- Test the acceptance of transactions coming from the IVR channel
  • B. 1- Test the acceptance of transactions coming from the IVR channel
    2- Test the correct charge of the Smart Card with the required contents
    3- Test the correct pre-activation of the Smart Card
    4- Test the correct activation of the Smart Card
  • C. 1- Test the correct activation of the Smart Card
    2- Test the correct pre-activation of the Smart Card
    3- Test the correct charge of the Smart Card with the required contents
    4- Test the acceptance of transactions coming from the IVR channel
  • D. 1- Test the correct pre-activation of the Smart Card
    2- Test the correct charge of the Smart Card with the required contents
    3- Test the correct activation of the Smart Card
    4- Test the acceptance of transactions coming from the IVR channel

Answer: A

 

NEW QUESTION 33
Test Management
Which of the following statements best describes an appropriate approach for managing exploratory testing?
Number of correct responses: 1
K2 1 credit

  • A. Exploratory testing should not be managed because such testing is inherently unmanageable and not measurable
  • B. Define very detailed mission statements, which allow testing work to be broken into sessions of up to 10 minutes duration in which testing is guided by these mission statements
  • C. Define very generic charters to drive exploratory testing sessions of 2 days where testers are completely free to decide what to test
  • D. Break the testing work in 30 to 120 minutes sessions and use properly defined mission statements consisting of two or three sentences to guide testing during these sessions

Answer: D

 

NEW QUESTION 34
You are the Test Manager of a new project aimed at developing a software system that must be certified at level B of the DO-178B standard. The project will follow a V-Model software development life cycle and it will have four formal levels of testing: component, integration, system and acceptance testing.
You must produce the test plan documentation for this project by providing an adequate coordination across the four levels of testing in order to assure audit ability.
Which of the following answers would you expect to best describe how to organize the test plan?
K3 2 credits

  • A. Produce four separate detailed level test plans, one for each level, without a master test plan
  • B. Produce a master test plan that covers three levels (component, integration, system test) and a separate acceptance test plan
  • C. Produce a master test plan describing the relationship between the four levels, and four separate detailed level test plans, one for each level
  • D. Produce a single master test plan that covers in detail all four levels, describing the particular activities for all test levels

Answer: C

 

NEW QUESTION 35
Test Management
Based on the historical data of 5 past and similar projects, you have calculated these average numbers of defects detected in system testing:
- for each 10000 LOC (lines of code), 200 defects
- for each person-month of development team effort, 49 defects
You want to use this information to perform estimation for a new project.
The project manager tells you that he/she has estimated 20000 new LOC for this new project.
Four developers work for four months on this project before system testing.
During system testing, 797 defects are discovered.
Assume that the system test of this new project is using the same amount of work as spent in the past projects.
Based on this information only, which of the following statement is certainly true about this project?

  • A. The number of defects found during the system test phase on the new project is approximately proportional to the development team effort
  • B. 40000 LOC have been delivered to system testing (against the 20000 LOC planned by the project manager)
  • C. The code for the new project contains a higher defect density than the code of the past projects
  • D. More LOC than planned have been delivered to system testing with a higher defect density than the past projects

Answer: A

 

NEW QUESTION 36
......


ISQI CTAL-TM_Syll2012 Exam Syllabus Topics:

TopicDetails
Topic 1
  • Includes people in roles such as testers test analysts test engineers
Topic 2
  • User acceptance testers and software developers
Topic 3
  • Advanced Level qualify cation is also appropriate for anyone who wants a deeper understanding of software testing.

 

100% Free ISQI Certifications CTAL-TM_Syll2012 Dumps PDF Demo Cert Guide Cover: https://validexam.pass4cram.com/CTAL-TM_Syll2012-dumps-torrent.html